South Carolina District Court
Judge:Patrick Michael Duffy
Case #: 9:17-cv-00984
Nature of Suit190 Contract - Other Contract
Cause28:1332 Diversity-Breach of Contract
Case Filed:Apr 17, 2017
Terminated:May 02, 2018
Last checked: Saturday Oct 14, 2017 5:56 AM EDT
Defendant
Shawn Lather
Represented By
Jeffrey S Weathers
Jeffrey S Weathers Law Office
contact info
Defendant
Lather Construction Inc
Represented By
Jeffrey S Weathers
Jeffrey S Weathers Law Office
contact info
Plaintiff
Blueline Rental LLC
Represented By
Ryan Daniel Gilsenan
Womble Carlyle Sandridge And Rice LLP
contact info
Sean Houseal
Womble Carlyle Sandridge And Rice LLP
contact info


Docket last updated: 04/25/2024 11:59 PM EDT
Wednesday, May 02, 2018
30 30 misc Judgment Wed 05/02 3:45 PM
JUDGMENT in favor of BlueLine against Lather Construction, Inc., pursuant to the terms outlined in the final Order. (egra, )
Related: [-]
29 29 order Stipulation and Order Wed 05/02 3:36 PM
STIPULATION AND ORDER Final judgment is hereby entered on the claims and causes of action set forth in BlueLines Complaint in favor of BlueLine against Lather Construction, Inc., pursuant to the terms of this Order. Signed by Honorable Patrick Michael Duffy on 05/02/2018. (egra, )
Related: [-]
Tuesday, May 01, 2018
28 28 misc Stipulation Tue 05/01 2:21 PM
DELETION OF DOCKET ENTRY NUMBER 28 Reason: Proposed order was e-mailed to Chambers. (egra, )
Related: [-]
Thursday, November 16, 2017
27 27 misc Reply Not to a Motion Thu 11/16 3:59 PM
REPLY by Shawn Lather, Lather Construction Inc . (Weathers, Jeffrey)
Related: [-]
Monday, November 13, 2017
25 25 order Scheduling Order Mon 11/13 11:09 AM
SECOND CONSENT AMENDED SCHEDULING ORDER: Plaintiffs ID of Expert Witness due by 2/15/2017, Defendants ID of Expert Witnesses Due by 3/15/2017, Records Custodian Affidavit due by 4/20/2018, Discovery due by 4/20/2018, Motion in Limine due by 6/18/2018, Motions due by 5/19/2018, Rule 26(a)(3) Disclosures due by 6/8/2018, Pretrial Briefs due by 6/11/2018, Jury Selection Deadline 6/18/2018, Mediation Due by 6/1/2018. Signed by Honorable Patrick Michael Duffy on 11/13/17. (chub, )
Related: [-]
Friday, November 10, 2017
24 24 motion Amend/Correct Fri 11/10 10:17 AM
Consent MOTION to Amend/Correct14 Scheduling Order,, and for Entry of a Second Consent Amended Scheduling Order, by Blueline Rental LLC. Response to Motion due by 11/27/2017. Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6 or Fed. R. Crim. P. 45.Proposed order is being emailed to chambers with copy to opposing counsel.(Gilsenan, Ryan)
Related: [-]
Att: 1 Proposed Order
Wednesday, November 08, 2017
23 23 motion Amend/Correct Wed 11/08 4:24 PM
MOTION to Amend/Correct14 Scheduling Order,, and to issue a Second Amended Scheduling Order, by Blueline Rental LLC. Response to Motion due by 11/22/2017. Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6 or Fed. R. Crim. P. 45.Proposed order is being emailed to chambers with copy to opposing counsel.(Gilsenan, Ryan)
Related: [-]
Att: 1 Proposed Order
22 22 misc Reply Not to a Motion Wed 11/08 1:21 PM
REPLY by Blueline Rental LLC to21 Order on Motion for Summary Judgment . (Gilsenan, Ryan)
Related: [-]
Tuesday, November 07, 2017
21 21 4 pgs order Order on Motion for Summary Judgment Tue 11/07 11:44 AM
ORDER granting in part and denying in part 15 Motion for Summary Judgment. Signed by Honorable Patrick Michael Duffy on November 7, 2017.(jmcg, )
Related: [-]
Thursday, October 05, 2017
20 20 respm Reply to Response to Motion Thu 10/05 1:04 PM
REPLY to Response to Motion re15 MOTION for Summary Judgment Response filed by Blueline Rental LLC.(Gilsenan, Ryan)
Related: [-]
Att: 1 Supporting Documents - Supplemental Declaration of Phillip Wright with exhibits E & F,
Att: 2 Supporting Documents - Declaration of Ryan Gilsenan with exhibits 1 & 2
Thursday, September 28, 2017
19 19 respm Response in Opposition to Motion Thu 09/28 1:16 PM
RESPONSE in Opposition re15 MOTION for Summary Judgment Response filed by Shawn Lather, Lather Construction Inc.Reply to Response to Motion due by 10/5/2017 Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6. (Weathers, Jeffrey)
Related: [-]
18 18 respm Response in Opposition to Motion Thu 09/28 2:11 PM
RESPONSE in Opposition re15 MOTION for Summary Judgment Response filed by Shawn Lather, Lather Construction Inc.Reply to Response to Motion due by 10/5/2017 Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6. (Weathers, Jeffrey) (egra, )
Related: [-]
Wednesday, September 13, 2017
17 17 order ~Util - Terminate Motions ~Util - Set Motion and R&R Deadlines/Hearings Wed 09/13 1:31 PM
ORDER granting 16 Motion for Extension of Time of 15 days to respond to Plaintiff's Motion for Summary Judgment.( Response to Motion due by 9/28/2017. Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6 or Fed. R. Crim. P. 45. ) Signed by Honorable Patrick Michael Duffy on 9/13/17. (cper, ) (cper, )
Related: [-]
Tuesday, September 12, 2017
16 16 motion Extension of Time Tue 09/12 8:43 PM
MOTION for Extension of Time by Shawn Lather, Lather Construction Inc. Response to Motion due by 9/26/2017. Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6 or Fed. R. Crim. P. 45. No proposed order.(Weathers, Jeffrey)
Related: [-]
Wednesday, August 30, 2017
15 15 motion Summary Judgment Wed 08/30 4:42 PM
MOTION for Summary Judgment by Blueline Rental LLC. Response to Motion due by 9/13/2017. Add an additional 3 days only if served by mail or otherwise allowed under Fed. R. Civ. P. 6 or Fed. R. Crim. P. 45.No proposed order.(Gilsenan, Ryan)
Related: [-]
Att: 1 Exhibit 1 - Declaration of Phillip Wright,
Att: 2 Exhibit 2 - BlueLine's Requests for Admission,
Att: 3 Exhibit 3 - Email correspondence
Monday, June 19, 2017
14 14 order Scheduling Order Mon 06/19 4:27 PM
FIRST CONSENT AMENDED SCHEDULING ORDER: Motions to Amend Pleadings due by 7/30/2017, Plaintiffs ID of Expert Witness due by 8/31/2017, Defendants ID of Expert Witnesses Due by 10/2/2017, Records Custodian Affidavit due by 12/15/2017, Discovery due by 12/15/2017, Motion in Limine due by 1/30/2018, Motions due by 1/30/2018, Rule 26(a)(3) Disclosures due by 2/20/2018, Pretrial Briefs due by 2/23/2018, Jury Selection Deadline 3/1/2018, Mediation Due by 2/15/2018. Signed by Honorable Patrick Michael Duffy on 6/19/17. (chub, )
Related: [-]
13 13 discov Local Rule 26.03 Answers to Interrogatories Mon 06/19 4:00 PM
Joint Local Rule 26.03 Answers to Interrogatories by Blueline Rental LLC.(Gilsenan, Ryan)
Related: [-]
12 12 discov Rule 26(f) Report Mon 06/19 3:58 PM
Joint Rule 26(f) Report by Blueline Rental LLC.(Gilsenan, Ryan)
Related: [-]
Att: 1 Proposed Order First Consent Amended Scheduling Order
Monday, May 15, 2017
11 11 order Scheduling Order Mon 05/15 2:58 PM
SCHEDULING ORDER: Rule 26(f) Conference Deadline 6/5/2017, 26(a) Initial Disclosures due by 6/19/2017, Rule 26 Report due by 6/19/2017, Motions to Amend Pleadings due by 7/7/2017, Plaintiffs ID of Expert Witness due by 8/7/2017, Defendants ID of Expert Witnesses Due by 9/5/2017, Records Custodian Affidavit due by 9/5/2017, Discovery due by 11/6/2017, Motion in Limine due by 2/8/2018, Motions due by 11/20/2017, Rule 26(a)(3) Disclosures due by 2/2/2018, Pretrial Briefs due by 2/23/2018, Jury Selection Deadline 3/1/2018, Mediation Due by 1/18/2018. Signed by Honorable Patrick Michael Duffy on 5/15/17. (chub, )
Related: [-]
Sunday, May 07, 2017
10 10 discov Local Rule 26.01 Answers to Interrogatories Mon 05/08 9:37 AM
Local Rule 26.01 Answers to Interrogatories by Lather Construction Inc. (Weathers, Jeffrey)(egra, )
Related: [-]
9 9 discov Local Rule 26.01 Answers to Interrogatories Mon 05/08 9:36 AM
Local Rule 26.01 Answers to Interrogatories by Shawn Lather. (Weathers, Jeffrey) (egra, )
Related: [-]
8 8 answer Answer to Complaint Sun 05/07 5:09 PM
ANSWER to Complaint by Lather Construction Inc.(Weathers, Jeffrey) Modified on 5/8/2017 to file attachment as separate entry10 (egra, )
Related: [-]
7 7 answer Answer to Complaint Sun 05/07 5:08 PM
ANSWER to Complaint by Shawn Lather.(Weathers, Jeffrey) Modified on 5/8/2017 to file attachment as separate entry9 (egra, )
Related: [-]
Monday, May 01, 2017
6 6 service Certificate of Service Mon 05/01 5:29 PM
SUMMONS Returned Executed by Blueline Rental LLC. Shawn Lather served on 4/24/2017, answer due 5/15/2017. (Gilsenan, Ryan) (egra, )
Related: [-]
Att: 1 Affidavit of Service
5 5 service Certificate of Service Mon 05/01 5:27 PM
SUMMONS Returned Executed by Blueline Rental LLC. Lather Construction Inc served on 4/24/2017, answer due 5/15/2017. (Gilsenan, Ryan) (egra, )
Related: [-]
Att: 1 Affidavit of Service
Monday, April 17, 2017
4 4 discov Local Rule 26.01 Answers to Interrogatories Tue 04/18 8:57 AM
Local Rule 26.01 Answers to Interrogatories by Blueline Rental LLC. (egra, )
Related: [-]
2 2 service Summons Issued Tue 04/18 8:56 AM
Summons Issued as to Shawn Lather, Lather Construction Inc. (egra, )
Related: [-]
Att: 1 Summons - Shawn Lather
1 1 cmp Complaint Tue 04/18 8:56 AM
COMPLAINT against Shawn Lather, Lather Construction Inc ( Filing fee $ 400 receipt number 0420-7105317.), filed by Blueline Rental LLC. Service due by 7/17/2017. (egra, )