Starnes et al v. Madewell Concrete, LLC et al
Georgia Northern District Court | |
Judge: | Thomas W Thrash, Jr |
Case #: | 1:24-cv-04111 |
Nature of Suit | 190 Contract - Other Contract |
Cause | 28:1446 Notice of Removal - Breach of Contract |
Case Filed: | Sep 12, 2024 |
Last checked: Tuesday Mar 11, 2025 4:28 AM EDT |
Defendant
John Does I-III
|
|
Defendant
Kevin Johnston
|
Represented By
|
Defendant
Madewell Concrete, LLC
|
Represented By
|
Plaintiff
Suzanne Estes
|
Represented By
|
Plaintiff
Chris Nesbitt
|
Represented By
|
Plaintiff
Luke Starnes
|
Represented By
|
Plaintiff
Maureen Starnes
|
Represented By
|
Docket last updated: 5 hours ago |
Friday, October 11, 2024 | ||
7 | 7
![]() ORDER granting6 Consent MOTION to Stay Case and MOTION to Compel Arbitration. The Court compels arbitration pursuant to the parties' Arbitration Agreement. If the parties are unable to select an arbitrator, they may apply to the Court to designate and appoint an arbitrator. Defendants' Motion to Compel Arbitration and, Alternatively, to Dismiss (Doc.2 ) is denied without prejudice as moot. Signed by Judge Thomas W. Thrash, Jr. on 10/11/2024. (bmr) |
|
Thursday, October 10, 2024 | ||
6 | 6
![]() Consent MOTION to Stay Case and Compel Arbitration by Kevin Johnston, Madewell Concrete, LLC.(Welch, T.) |
|
Att: 1
![]() |
||
Thursday, September 26, 2024 | ||
5 | 5
![]() ORDER granting4 Consent MOTION for Extension of Time for Response to2 MOTION to Compel Arbitration. It is hereby ORDERED that the deadline for responses to the Motion is extended by and through 10/11/2024. Signed by Judge Thomas W. Thrash, Jr. on 09/26/2024. (bmr) |
|
Wednesday, September 25, 2024 | ||
4 | 4
![]() Consent MOTION for Extension of Time for Response to Pending Motion re:2 MOTION to Compel ArbitrationMOTION to Dismiss by Kevin Johnston, Madewell Concrete, LLC.(Welch, T.) |
|
Att: 1
![]() |
||
Friday, September 13, 2024 | ||
3 | 3
![]() Letter from Clerk re: LR 83.1 Attorney Admission requirements sent to Wesley A. Pickelsimer. Clerk to follow-up by 9/23/2024. (cpp) |
|
Thursday, September 12, 2024 | ||
2 | 2
![]() MOTION to Compel Arbitration and, Alternatively, MOTION to Dismiss with Brief In Support by Kevin Johnston, Madewell Concrete, LLC.(tcc) |
|
Att: 1
![]() |
||
Att: 2
![]() |
||
Att: 3
![]() |
||
Att: 4
![]() |
||
1 | 1
![]() NOTICE OF REMOVAL with COMPLAINT filed by Kevin Johnston, Madewell Concrete, LLC. (Filing fee $ 405 receipt number AGANDC-13716998)(tcc) |
|
Att: 1
![]() |
||
Att: 2
![]() |